A prefabricated pump station leaves the workshop as a finished assembly - tank, pump set, guide rails, internal piping, valves and control panel already matched and tested. What happens in the next few days on site decides whether that factory quality survives into service. On the station shown here, these are the six steps we work to - and the points where projects most often go wrong.

1. Pit and base: the station is only as level as its foundation
- Excavate to the design depth and keep the pit dewatered throughout handling and backfill.
- Sheet piles, trench boxes or benched slopes are chosen according to soil and adjacent structures; on urban sites the excavation is often fully supported.
- Place a levelled sand or gravel bed and check it with a straightedge before the unit arrives - a tank seated on an uneven base carries permanent stress in the shell.
- Where groundwater is high, the anti-flotation design - base slab, anchor lugs or ballast - is installed before, not after, the tank goes in.
2. Lifting: one piece, correct lugs, no pipe slings
- Lift only from the designated lifting lugs. Never sling from nozzles, rails or the discharge pipe.
- Keep the unit vertical during the descent and lower it slowly; a person at the pit edge confirms alignment with the inlet and outlet stubs.
- The station is set down as a single assembly, so the crane or excavator capacity is matched to the complete weight - including any water left in the tank.


3. Connections: let the pipe follow the tank, not the tank follow the pipe
- Inlet and outlet connections are made with flexible couplings so that settlement and thermal movement do not load the tank wall.
- External pipework is supported independently; the tank must not carry the weight of backfilled pipes or valves.
- Check the inlet invert and discharge level against the drawings before backfilling - correcting them afterwards means lifting the unit out again.
4. Backfill: symmetric, in layers, and never against one wall only
- Backfill with the specified granular material in thin layers, compacted on both sides at the same rate so the shell is not pushed out of shape.
- Backfill is brought up evenly around the tank; dropping material from height onto the shell is avoided.
- Where the station sits in saturated ground, backfill and anti-flotation works are completed before the pit is allowed to flood.

5. Electrical works and commissioning
- The control cabinet is mounted above ground on a plinth, clear of flood level, with the cable route protected from water ingress.
- Level signals - float switches, pressure transmitters or ultrasonic sensors - are set to the actual wet-well levels of the project, not left at factory defaults.
- Each pump is bumped to confirm rotation, then run on dry-run protection, overload and high-level alarm tests before the station is handed over.
- Duty and standby changeover, telemetry and remote alarm contacts are verified with the client's operator present.
6. Handover and after-sales
- As-built drawings, test records, operating instructions and spare parts list are handed over with the station.
- Operators are trained on the panel, the manual override and the alarm response.
- A first inspection visit after the station has seen real flows confirms levels, pump run-times and alarm behaviour while the site is still under warranty.

Typical applications
Residential and commercial rainwater drainage · Municipal sewage lifting · Urban stormwater and flood pumping · Underground car park drainage · Township and rural wastewater collection · Water supply booster stations
Ordering a station is the easy part; getting it into the ground correctly is where projects are won. Send us your pit dimensions, invert levels and site access conditions, and our engineers will confirm the installation sequence and lifting plan for your project.
Contact KORE
Tel / Hotline: +86 400-820-7055
Email: silas@korepumpstation.com
Web: www.korepumpstation.com
Manufacturer: Shanghai Kelei Fluid Automatic Control Equipment Manufacturing Co., Ltd
Hashtags
#PrefabricatedPumpStation #GRPPumpStation #PumpStationInstallation #Commissioning #SewageLiftingStation #StormwaterPumpStation #WaterInfrastructure #ConstructionSite #PumpManufacturer #KOREFluidControls